Skip to content
Early access — you're among the first to try PYQLabs. Share feedback

GATE Civil Engineering

2,198 questions · 40 years · 34 subjects

Public preview: use this branch page to find high-signal topics and keyed questions. Explanations are being added selectively, starting with recent and recurring concepts.

High-yield topics

All trends →

Practice Civil Engineering PYQs

26 questions shown in Construction Material and Management. Filter for cleaner practice sessions.

Showing Construction Material and Management PYQs from Civil Engineering.
2025 PYQ

Consider the following statements $(P)$ and $(Q)$ : $(P):$ Fly ash and ground granulated blast furnace slag can be used as mineral admixtures in concrete. (Q): As per IS 456:2000,...

Construction Material and Management/STMT/answer key/explanation
2025 PYQ

In the context of construction project management, which of the following statements is/are true:

Construction Material and Management/MSQ/answer key/explanation
2025 PYQ

In the context of testing bitumen, which one of the following statements is FALSE:

Construction Material and Management/MCQ/answer key/explanation
2025 PYQ

If the weights retained on the $2.36 \mathrm{~mm}, 1.18 \mathrm{~mm}, 600 \mu \mathrm{~m}$, and $300 \mu \mathrm{~m}$ sieves are $30 \%$, $35 \%, 15 \%$, and $20 \%$, respectively,...

Construction Material and Management/NAT/explanation
2025 PYQ

Identify the FALSE statement from the following options:

Construction Material and Management/MCQ/answer key/explanation
2025 PYQ

During determination of the bulk specific gravity of compacted bituminous specimen, the mass in air of the specimen is 1260 g and volume is $525 \mathrm{~cm}^3$. The density of wat...

Construction Material and Management/NAT/explanation
2024 PYQ

Consider the statements P and Q. P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase. Q: Client’s Detailed Estimate is used for...

Construction Material and Management/STMT/answer key/explanation
2024 PYQ

Consider the following data for a project of 300 days duration. Budgeted Cost of Work Scheduled (BCWS) = Rs. 200 Budgeted Cost of Work Performed (BCWP) = Rs. 150 Actual Cost of Wor...

Construction Material and Management/MCQ/answer key/explanation
2024 PYQ

The table shows the activities and their durations and dependencies in a project. Activity Duration (Days) Depends on A 8 - B 4 A C 4 B D 4 C, L F 4 A G 4 F H 6 G, L K 10 A L 6 F,...

Construction Material and Management/NAT/explanation
2024 PYQ

Concrete of characteristic strength 30 MPa is required. If 40 specimens of concrete cubes are to be tested, the minimum number of specimens having at least 30 MPa strength should b...

Construction Material and Management/MCQ/answer key/explanation
2024 PYQ

Consider the statements P and Q. P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project. Q: A Matrix organizat...

Construction Material and Management/STMT/answer key/explanation
2024 PYQ

In the context of pavement material characterization, the CORRECT statement(s) is/are

Construction Material and Management/MSQ/answer key/explanation
2024 PYQ

Which one of the following statements related to bitumen is FALSE?

Construction Material and Management/MCQ/answer key/explanation
2024 PYQ

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount o...

Construction Material and Management/STMT/answer key/explanation
2023 PYQ

M20 concrete as per IS 456: 2000 refers to concrete with a design mix having _______.

Construction Material and Management/MCQ/answer key/explanation
2023 PYQ

In cement concrete mix design, with the increase in water-cement ratio, which one of the following statements is TRUE?

Construction Material and Management/MCQ/answer key/explanation
2022 PYQ

The project activities are given in the following table along with the duration and dependency. Activities Duration (days) Depends on P 10 - Q 12 - R 5 P S 10 Q T 10 P, Q Which one...

Construction Material and Management/MCQ/answer key/explanation
2022 PYQ

Match all the possible combinations between Column X (Cement compounds) and Column Y (Cement properties) : Column X Column Y (i) $${C_3}S$$ (P) Early age strength (ii) $${C_2}S$$ (...

Construction Material and Management/MTF/answer key/explanation
2022 PYQ

The activities of a project are given in the following table along with their durations and dependency. Activities Duration (day) Depends on A 10 - B 12 - C 15 A D 14 B E 10 B, C T...

Construction Material and Management/NAT/explanation
2022 PYQ

Which of the following equations is correct for the Pozzolanic reaction?

Construction Material and Management/MCQ/answer key/explanation
2017 PYQ

Consider the following statements: P. Walls of one brick thick are measured in square meters. Q. Walls of one brick thick are measured in cubic meters. R. No deduction in the brick...

Construction Material and Management/STMT/answer key
2017 PYQ

Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be...

Construction Material and Management/MCQ/answer key
2017 PYQ

For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard...

Construction Material and Management/NAT
2016 PYQ

The compound which is largely responsible for initial setting and early strength gain of Ordinary Portland Cement is

Construction Material and Management/MCQ/answer key
2016 PYQ

As per Indian standards for bricks, minimum acceptable compressive strength of any class of burnt clay bricks in dry state is

Construction Material and Management/MCQ/answer key
2016 PYQ

Bull's trench kiln is used in the manufacturing of

Construction Material and Management/MCQ/answer key