The maximum level of inventory of item is $$100$$ and it is achieved with infinite replenishment rate. The inventory becomes zero over one and half month due to consumption at a un...
mediumanswer key
1996 PYQ
In an assembly line for assembling toys, five workers are assigned tasks which take times of $$10, 8, 6, 9$$ and $$10$$ minutes respectively. The balance delay for the line is
easyanswer key