power generation
GATE Electrical Engineering · Generation & Transmission · 1996-2025
Study anchor
Source-book anchor pending for this concept.
Practice action
Start latest PYQPYQs in this concept
All concepts →Two units, rated at 100 MW and 150 MW, are enabled for economic load dispatch. When the overall incremental cost is 10,000 Rs./MWh, the units are dispatched to 50 MW and 80 MW resp...
The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by Plant 1 : C 1 = 350 + 6P 1 + 0.004P$$_1^2$$ Plant 2 : C 2 = 450 + aP 2 + 0.003P$$_2^2$$ wher...
Consider the economic dispatch problem for a power plant having two generating units. The fuel costs in $$Rs/MWh$$ along with the generation limits for the two units are given belo...
In thermal power plants, the pressure in the working fluid cycle is developed by
For harnessing low variable water heads, the suitable hydraulic turbine with high percentage of reaction and runner adjustable vanes is
Incremental fuel costs (in some appropriate unit) for a power plant consisting of three generating units are $${\rm I}{C_1} = 20 + 0.3\,\,{P_1},\,{\rm I}{C_2} = 30 + 0.4\,\,{P_2},\...
In a thermal power plant, the feed water coming to the economiser is heated using
Which material is used in controlling chain reaction in a nuclear reactor?