Project Management - PERT/CPM
GATE Civil Engineering · 3 questions across 2 years (2018-2021) · 5% recurrence rate
Recurrence sparkline
2018–2021Difficulty mix
Question types
All 3 questions on Project Management - PERT/CPM
The activity details for a small project are given in the Table. Activity | Duration (days) | Depends on A | 6 | - B | 10 | A C | 14 | A D | 8 | B E | 12 | C F | 8 | C G | 16 | D, E H | 8 | F, G K | 2 | B L | 5 | G, K Th...
A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table. Activity | Duration (in weeks) | Depends up...
The activity details of a project are given below: Activity | Depends on | Duration (in days) ---|---|--- P | -- | 6 Q | P | 15 R | Q, T | 12 S | R | 16 T | P | 10 U | Q, T | 14 V | U | 16 The estimated minimum time (in...