water budget
GATE Civil Engineering · Hydrologic Cycle · 2002-2015
2
PYQs
100%
keyed
0
elite explanations
2
years appeared
Study anchor
Source-book anchor pending for this concept.
Practice action
Start latest PYQPYQs in this concept
All concepts →2015 PYQ
The average surface area of a reservoir in the month of June is 20 km 2 . In the same month, the average rate of inflow is 10 m 3 /s, outflow rate is 15 m 3 /s, monthly rainfall is...
mediumanswer key
2002 PYQ
During a 6-hour storm the rainfall intensity was 0.8 cm/hr on a catchment of area 8.6 km 2 . The measured runoff volume during this period was 2,56,000 m 3 . The total rainfall was...
easyanswer key