PYQs in this concept

All concepts →
2025 Q42

In the context of construction project management, which of the following statements is/are true:

mediumanswer key
2025 PYQ

In the context of construction project management, which of the following statements is/are true:

easyanswer keyelite explanation
2024 Q16

Consider the statements P and Q. P: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase. Q: Client's Detailed Estimate is used for...

mediumanswer key
2024 Q17

Consider the statements P and Q. P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project. Q: A Matrix organizat...

mediumanswer key
2024 Q19

Consider the following data for a project of 300 days duration. Budgeted Cost of Work Scheduled (BCWS) = Rs. 200 Budgeted Cost of Work Performed (BCWP) = Rs. 150 Actual Cost of Wor...

mediumanswer key
2024 Q38

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount o...

mediumanswer key
2024 PYQ

Consider the following data for a project of 300 days duration. Budgeted Cost of Work Scheduled (BCWS) = Rs. 200 Budgeted Cost of Work Performed (BCWP) = Rs. 150 Actual Cost of Wor...

easyanswer keyelite explanation
2024 PYQ

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount o...

easyanswer keyelite explanation
2024 PYQ

The table shows the activities and their durations and dependencies in a project. Activity Duration (Days) Depends on A 8 - B 4 A C 4 B D 4 C, L F 4 A G 4 F H 6 G, L K 10 A L 6 F,...

mediumelite explanation
2022 Q39

The project activities are given in the following table along with the duration and dependency. Activities | Duration (days) | Depends on ---|---|--- P | 10 | - Q | 12 | - R | 5 |...

mediumanswer key
2022 Q53

The activities of a project are given in the following table along with their durations and dependency. The total float of the activity E (in days) is __________. (in integer)

mediumanswer key
2022 PYQ

The project activities are given in the following table along with the duration and dependency. Activities Duration (days) Depends on P 10 - Q 12 - R 5 P S 10 Q T 10 P, Q Which one...

easyanswer keyelite explanation
2022 PYQ

The activities of a project are given in the following table along with their durations and dependency. Activities Duration (day) Depends on A 10 - B 12 - C 15 A D 14 B E 10 B, C T...

easyelite explanation
2021 Q42

The activity details for a small project are given in the Table. Activity | Duration (days) | Depends on A | 6 | - B | 10 | A C | 14 | A D | 8 | B E | 12 | C F | 8 | C G | 16 | D,...

mediumanswer key
2021 Q43

A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table. Act...

mediumanswer key
2018 Q45

The activity details of a project are given below: Activity | Depends on | Duration (in days) ---|---|--- P | -- | 6 Q | P | 15 R | Q, T | 12 S | R | 16 T | P | 10 U | Q, T | 14 V...

mediumanswer key
2017 PYQ

For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard...

easyelite explanation