markup
GATE Civil Engineering · Construction Management - Cost Estimation · 2021-2021
2
PYQs
100%
keyed
0
elite explanations
1
years appeared
Study anchor
Source-book anchor pending for this concept.
Practice action
Start latest PYQPYQs in this concept
All concepts →2021 Q6
The direct and indirect costs estimated by a contractor for bidding a project is ₹160000 and ₹20000 respectively. If the mark up applied is 10% of the bid price, the quoted price (...
mediumanswer key
2021 Q30
Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Con...