A post-tensioned concrete member of span 15 m and cross-section of 450 mm $$\times$$ 450 mm is prestressed with three steel tendons, each of cross-sectional area 200 mm 2 . The ten...
mediumanswer keybasic explanation
2017 PYQ
A pre-tensioned rectangular concrete beam $$150$$ $$mm$$ wide and $$300$$ $$mm$$ depth is prestressed with three straight tendones, each having a cross-sectional area of $$50$$ $$m...
medium
2008 PYQ
A pre-tensioned concrete member of section $$200\,\,mm \times 250\,\,mm$$ contains tendons of area $$500\,\,m{m^2}$$ at the centre of gravity of the section. The prestress in tendo...
mediumanswer key
1992 PYQ
The loss of prestress due to elastic shortening of concrete is least in