PYQs in this concept

All concepts →
2025 Q53

The figure shows a network diagram for a construction project. The activities A, B, C, D, E, and F are represented by arrows and their durations are in the figure. The total float...

mediumanswer key
2025 PYQ

In the context of construction project management, which of the following statements is/are true:

easyanswer keyelite explanation
2024 Q52

The table shows the activities and their durations and dependencies in a project. Activity | Duration (Days) | Depends on A | 8 | - B | 4 | A C | 4 | B D | 4 | C, L F | 4 | A G | 4...

mediumanswer key
2024 PYQ

The table shows the activities and their durations and dependencies in a project. Activity Duration (Days) Depends on A 8 - B 4 A C 4 B D 4 C, L F 4 A G 4 F H 6 G, L K 10 A L 6 F,...

mediumelite explanation
2022 Q39

The project activities are given in the following table along with the duration and dependency. Activities | Duration (days) | Depends on ---|---|--- P | 10 | - Q | 12 | - R | 5 |...

mediumanswer key
2022 Q53

The activities of a project are given in the following table along with their durations and dependency. The total float of the activity E (in days) is __________. (in integer)

mediumanswer key
2022 PYQ

The activities of a project are given in the following table along with their durations and dependency. Activities Duration (day) Depends on A 10 - B 12 - C 15 A D 14 B E 10 B, C T...

easyelite explanation
2021 Q42

The activity details for a small project are given in the Table. Activity | Duration (days) | Depends on A | 6 | - B | 10 | A C | 14 | A D | 8 | B E | 12 | C F | 8 | C G | 16 | D,...

mediumanswer key
2021 Q43

A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table. Act...

mediumanswer key
2019 Q37

The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the ac...

hardanswer key
2018 Q45

The activity details of a project are given below: Activity | Depends on | Duration (in days) ---|---|--- P | -- | 6 Q | P | 15 R | Q, T | 12 S | R | 16 T | P | 10 U | Q, T | 14 V...

mediumanswer key