All concepts →For a clayey soil stratum, the time required for degree of consolidation from 25 % to 50 % is 30 days. The total time (in days) required for 90 % degree of consolidation of the sam...
A 6 m thick clay stratum has drainage at both its top and bottom surface due to the presence of sand strata. The time to complete 50% consolidation is 2 years. The coefficient of v...
In an oedometer apparatus a specimen of fully saturated clay has been consolidated under a vertical pressure of 100 kPa and is at equilibrium state. Immediately on increasing the v...
A 6 m thick clay stratum has drainage at both its top and bottom surface due to the presence of sand strata. The time to complete $50 \%$ consolidation is 2 years. The coefficient...
The total primary consolidation settlement (S_c) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the construction of the...
The total primary consolidation settlement ($S_c$) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the construction of th...
A saturated compressible clay layer of thickness h is sandwiched between two sand layers, as shown in the figure. Initially, the total vertical stress and pore water pressure at po...
A raft foundation of 30 m × 25 m is proposed to be constructed at a depth of 8 m in a sand layer. A 25 m thick saturated clay layer exists 2 m below the base of the raft foundation...
In an Oedometer apparatus, a specimen of fully saturated clay has been consolidated under a vertical pressure of 50 kN/m² and is presently at equilibrium. The effective stress and...
A clay layer of thickness H has a preconsolidation pressure $p_c$ and an initial void ratio $e_0$. The initial effective overburden stress at the mid-height of the layer is $p_0$....
The soil profile at a construction site is shown in the figure (not to scale). Ground water table (GWT) is at 5 m below the ground level at present. An old well data shows that the...
The soil profile at a road construction site is as shown in figure (not to scale). A large embankment is to be constructed at the site. The ground water table (GWT) is located at t...
The void ratio of a clay soil sample M decreased from 0.575 to 0.510 when the applied pressure is increased from 120 kPa to 180 kPa. For the same increment in pressure, the void ra...
A 10 m thick clay layer is resting over a 3 m thick sand layer and is submerged. A fill of 2 m thick sand with unit weight of 20 kN/m³ is placed above the clay layer to accelerate...
A 3 m thick clay layer is subjected to an initial uniform pore pressure of 145 kPa as shown in the figure. For the given ground conditions, the time (in days, rounded to the neares...