Concept drill
canal
GATE Civil Engineering · Irrigation Engineering - Canal Design · 2023-2026
3
PYQs
67%
keyed
0
elite explanations
3
years appeared
Study anchor
Source-book anchor pending for this concept.
Practice action
Start latest PYQPYQs in this concept
All concepts →2026 Q17
An irrigation canal is to be designed to deliver 10 cumec to meet the peak demand of 7500 hectare of cropped area. The estimated canal losses are 50 % of the head discharge. The du...
mediumanswer key
2025 Q61
A symmetrical trapezoidal canal is 100 km long. The bottom width is 10 m and the side slope is 1 Horizontal : 1 Vertical. The average flow depth in the canal is 2.5 m throughout th...
mediumanswer key
2023 PYQ
A canal supplies water to an area growing wheat over 100 hectares. The duration between the first and last watering is 120 days, and the total depth of water required by the crop i...
mediumbasic explanation